IN PROGRESS · GAIBANDHA · FOUR CHARS

EcoChar

Site and baseline work for two projects across four river islands in Gaibandha. Field update: July 2026.

See current work
PROJECT 01Char UdayanKamarjani + Mollarchar
PROJECT 02Adaptive Eco CharFazlupur + Fulchhari

CHAR CONTEXT

Infrastructure has to work where the river keeps rewriting access

The two projects cover storage, solar energy, water, transport, growing support and local enterprise across four river islands in Gaibandha. July’s records focus on land, baselines and engineering readiness.

Bangladesh district atlas with Gaibandha highlighted

Gaibandha district · 2024–25 BBS production records

CROP INTELLIGENCE · GAIBANDHA

Gaibandha’s recorded crop production

POTATO367,101 t#10 of 64 recorded districts · 14,185 ha
MAIZE158,849 t#11 of 64 · 12,950 ha
BANANA29,215 t#8 of 64 · 1,385 ha

District records do not establish participant crop mix, char-level production or EcoChar outcomes.

Open Gaibandha in Crop Intelligence →
PLANNED DELIVERY

The two projects move on separate schedules

PROJECT 01

Char Udayan

Kamarjani + Mollarchar · Jul 2026 to Dec 2027 · 1,000 households to reach

2Udayan HubsZECC + digital connectivity
4Solar irrigation systems
Hybrid boatsCargo + rescue transport
Farm toolsMachinery + shellers
ConnectivityStarlink + solar power
15 batchesTechnical trainingLivelihoods + market access
PROJECT 02

Adaptive Eco Char

Fazlupur + Fulchhari · May 2026 to Mar 2028

2 + 2Resilience hubs + eco-storage
200Household solar systems
2 + 2Water purification + digital health
600 peopleClimate-smart growingSandbar crops + homestead gardens
150 householdsLivestock support
200 womenChar enterprises
IMPLEMENTATION · JULY 2026VERIFIED · 31 JULY 2026

Land, baseline and engineering come first

CHAR UDAYAN · GAIBANDHA SADAR

Site certainty comes before procurement

In place
Implementation plans prepared; four potential sites assessed; consultation held; baseline questionnaire finalised; supplier bills of quantities collected.
What is delaying work
Final site confirmation, baseline completion, heavy rain, erosion exposure and incomplete land documents.
Next step
Complete the baseline, confirm the hub site, verify beneficiaries and move procurement forward.
ADAPTIVE ECO CHAR · FULCHHARI

Selected sites still have to clear land and engineering

In place
Sixteen consultations completed; infrastructure sites selected; supplier bills of quantities collected; regional crop assessment completed.
What is delaying work
Land transfer, engineering, baseline and beneficiary selection, flood-safe land availability and land-use documents.
Next step
Complete land transfer and baseline work, finalise engineering and launch procurement.

JULY FIELD RECORD

Site records and consultations

CHAR UDAYAN

Four potential hub sites were assessed

  • Implementation, action and technical site-selection records were prepared.
  • Four potential sites were assessed for two Udayan Hubs.
  • Community consultation was documented and the baseline questionnaire was finalised.
ADAPTIVE ECO CHAR

Infrastructure sites were selected

  • Sixteen consultations were documented across the two project unions.
  • Infrastructure sites, supplier bills of quantities and the regional crop assessment were recorded.
  • Baseline and beneficiary selection were underway.
Community consultation documented for Char Udayan during July 2026
CHAR UDAYAN · COMMUNITY CONSULTATION · JUL 2026

Community consultation.

Agricultural site context documented for Char Udayan during July 2026
CHAR UDAYAN · SITE CONTEXT · JUL 2026

Land condition informed site screening.

Each project keeps its own field record

Photos shown here are from Char Udayan, July 2026.

CHAR UDAYAN · ALLOCATION

Where the funding goes

Adaptive Eco Char is funded separately and retains its own allocation.

Capital assets
66.2%
Hubs, irrigation, boats, machinery + connectivity
Programme activities
27.3%
Training, enterprise support, drills + monitoring
Overhead + HR
6.5%
Project management
CURRENT CONSTRAINT

Flood-safe sites narrow the options

Land arrangements must be clear before construction. Heavy rain and incomplete documentation slowed site work in July; erosion and scarce elevated land narrowed the options.

NEXT

Next steps for each char project

CHAR UDAYAN

Complete the baseline, confirm the Udayan Hub site, verify beneficiaries and advance procurement planning.

ADAPTIVE ECO CHAR

Complete land transfer, baselines and engineering. Begin construction once procurement clears.

Confirm land arrangements and baseline records at each char site before procurement or construction.